本方案为深圳地铁5 号线BT 项目给排水施工方案,共20页,PDF
目录
一、施工策划·········································································································································································· 2
( 1)项目概要····························································································································································2
( 2)施工部署····························································································································································2
二、编制依据·········································································································································································· 3
三、施工机具·········································································································································································· 3
四、经济评估·········································································································································································· 3
五、给排水及消防工程施工工艺····································································································································· 3
( 1)给水排水系统的安装········································································································································3
( 2)
消防系统
的安装··············································································································································10
( 3)水泵安装··························································································································································13
六、给排水及消防系统调试方案··································································································································· 15
( 1)系统调试方法··················································································································································15
( 2)系统联合调试··················································································································································16
七、给排水、消防工程的成品、半成品的保护措施····································································································· 16
八、安全文明施工································································································································································ 17
项目概要
深圳地铁5 号线BT 项目由前海湾经宝安中心、新安旧城区、西丽、大学城、最后到黄贝岭。线路全长40.001km,其中 地下线路35.801 km,高架线路3.424 km,过渡段0.776km。共设27 座车站,其中地下站25 座,地上站2 座,平均站间距约1.454km。
本标段工程内容为五个地下站(前海湾站、临海路站、宝华路站、宝安中心站、翻身路站)四区间(前临区间、临宝区间、宝宝区间、宝翻区间)的安装、装修工程及其他附属工程。
四区间均为两条单洞单线隧道,多数是盾构掘进形成,局部为矿山法挖掘或明挖法形成。中间有联络通道、泵房、风井。
为保证不间断供水,车站给水系统分别从车站两端市政给水管上分别引出1 根DN150进水管(互为备用)作为车站生活、生产与消防用水。一路自水表井后变为DN150至车站消防管网,另一路从水表井后分别引出两根水管,一路DN100给水管供车站生产生活用水和冷却冷冻循环补充用水,一路DN150至车站消防管网,进入车站的每根进水管上均设置倒流防止器,生活给水管与消防水管的引入管均设水表。
车站生产生活日用水量271.1m3,最高日用水量416.4m3。其中,人员用水定额为50L/ 人·班,最高日用水为2.5m3。消火栓用水量20L/s ,火灾延续时间为2 小时,局部喷淋强度不应低于6L/min ·平方米,持续喷水时间不低于0.5h 。水消防系统进入车站后经水泵加压后接入车站消火栓管网,消火栓系统成环状管网。
室内给水管道安装工艺流程图
室内给水管道安装的技术措施
管道支架安装示意图
穿楼板防火封堵图