一、编制依据及范围........................................................2
-
1.1 编制依据.............................................................2
-
1.2 编制范围.............................................................2
-
二、工程地质及水文地质....................................................2
-
2.1工程地质..............................................................2
-
2.2 水文地质..............................................................4
-
三、端头加固方案..........................................................5
-
四、施工部署..............................................................7
-
4.1 组织机构.............................................................7
-
4.2 现场布置.............................................................7
-
4.3 施工安排.............................................................8
-
4.4 工期安排.............................................................8
-
4.5 劳动力计划...........................................................8
-
4.6 设备配置.............................................................8
-
五、旋喷桩施工............................................................9
-
5.1施工准备..............................................................9
-
5.2工艺流程..............................................................9
-
5.3旋喷桩施工...........................................................10
-
5.4质量控制.............................................................11
-
六、袖阀管注浆施工.......................................................13
-
6.1、施工方法和步骤......................................................14
-
6.2、注浆主要参数........................................................14
-
6.3、施工注意事项........................................................15
-
七、安全环保措施.........................................................16
-
7.1 安全措施.............................................................16
-
7.2 文明施工及环境保护措施...............................................18
-
八、端头地质柱状图.......................................................20
-
8.1、附图1:B8孔钻孔柱状图;.............................................20
-
8.2、附图2: B9孔钻孔柱状图..............................................21
附件详情
三、端头加固方案
始发端头加固方案为三重管旋喷桩与袖阀管注浆相结合的方式,加固水平长度为8m、宽度为洞门直径加左右各2m,共10m,加固深度为洞门底部以下2m,至洞门顶部以上4m,即单根桩长为12m。旋喷桩中心距为500mm,采用梅花型布置…………
五、旋喷桩施工
高压三重管旋喷施工技术,具有施工速度快,无渗水盲区,工程质量高,劳动强度低,材料消耗小等优点。高压三重管旋喷桩的工艺原理是用压缩空气包裹高压喷射水流冲击破坏搅动土体,同时用低压灌浆泵灌入浆液…………
5.3旋喷桩施工
钻进 钻孔严格按钻孔施工工艺进行,严格控制垂直度在允许范围之内。检测控制方法,用500ram金属水平尺两个垂直方向靠在主动钻杆上检测,不许超过5mm。个别孔斜稍有超差可在后续喷射工序适当调整参数予以弥补…………
提管旋喷 当喷射管达到预定地层后,先送空气、高压水,再将水泥浆送入孔中静喷少顷,待孔口回浆的比重>1.3g/cm开始提管,连续进行;若孔口回浆的比重<1.3 g/cm时,应降低提速或停止提管…………